Whispering Oaks Community

Infrastructure Improvements

A Firm Start = A Strong Finish

A comprehensive infrastructure improvement project serving the Whispering Oaks community in the Carrollwood area of Tampa. This project encompasses full-depth road milling and resurfacing, sidewalk replacement, driveway apron reconstruction, concrete grinding, and roundabout corrections — improving safety, accessibility, and curb appeal across 5 streets and 197 work areas. Estimated completion: 45 days.

197
Work Areas
5
Streets
268K SF
Road Surface
5,612 SF
Sidewalk
3,798 SF
Driveway
~45
Days to Complete

Project Overview

Road & Sidewalk Scope

Full-depth milling and resurfacing of approximately 268,000 square feet of roadway across 5 community streets. Replacement of 225 sidewalk panels comprising 5,612 square feet to restore safe pedestrian access, along with reconstruction of 27 driveway aprons and precision grinding of 112 concrete trip hazards totaling 448 linear feet — all performed to current ADA and municipal standards.

Roundabout Corrections

Remove current concrete barrier and existing pavers. Fix base by the drain — approximately 400 SF of base to be repaired and raised. Install new 5' wide by 163' perimeter 6" thick colored and stamped concrete, with color and stamp style to be discussed with client prior to the work being completed.

Project Timeline

Contract Signed

Mobilization & Setup

Sidewalk Replacement — 225 panels, 5,612 SF (~30 days)

Driveway Aprons — 27 areas

Concrete Grinding — 112 areas, 448 LF (~30 days)

Roundabout Corrections — 163 LF perimeter

Milling & Paving — Phase 1 (2 days)

Milling & Paving — Phase 2 (2 days)

Milling & Paving — Phase 3 (2 days)

Milling & Paving — Phase 4 (2 days)

Milling & Paving — Phase 5 (2 days)

Milling & Paving — Phase 6 (2 days)

Final Inspection & Completion

Scope Breakdown

Milling & Paving

268K SF

Full-depth milling and resurfacing across all 5 streets — 6 phases, 12 days

Sidewalk Replacement

225 Panels

5,612 SF of damaged or non-compliant sidewalk panel replacements

Driveway Aprons

27 Areas

3,798 SF of driveway reconstruction with proper grading and ADA transitions

Concrete Grinding

112 Areas

448 linear feet of precision grinding at trip hazard locations

Roundabout Corrections

163 LF

New stamped and colored concrete perimeter with base repairs